KC Mark Korea Certification - Induction Cooktop
● KC Conformity Registration (EMC)
Product | Induction Cooktop |
Power | AC Power |
Certification Type | KC Conformity Registration (EMC) |
Sample | 1 unit |
Lead Time | 2 to 3 weeks |
Required Document | User Manual |
Note | - |
● KC Safety Certification
Product | Induction Cooktop |
Power | AC Power |
Certification Type | KC Safety Certification |
Sample | 1 unit |
Lead Time | 45 days or less with CB |
Required Document | Korean User Manual, BOM, Component Specification, Schematics, Label sample, CB (if there is) |
Note | Products more than 30Vac or 42Vdc are related to KC safety. CB test report and certificate is accepted. This product requires factory inspection. |
● MEPS (Minimum Energy Performance Standard) Program
Product | Induction Cooktop |
Power | AC Power |
Certification Type | MEPS (Minimum Energy Performance Standard) Program |
Sample | 2 unit |
Lead Time | 2 to 3 weeks |
Required Document | User Manual |
Note | This is applied to products with a rated power consumption of 1kW or more and 10kW or less. You must report to the Korea Energy Agency within 90 days from either the date you receive the test report from the Energy Efficiency Testing Institute or the date you issue the test report after completing self-measurement. |
EMC / RF / SAR (KC)
Product Safety (KC)
Energy Efficiency (KC)
'Library' 카테고리의 다른 글
KC Certification - Electronic musical instruments (0) | 2023.12.11 |
---|---|
KC Certification - Vacuum cleaner (0) | 2023.12.05 |
KC Certification - Coffee Maker (0) | 2023.11.28 |
KC Certification - Blender (0) | 2023.11.21 |
KC Certification - Electric Dryer (1) | 2023.11.20 |